This site is not affiliated with AGCO Inc., Duluth GA., Allis-Chalmers Co., Milwaukee, WI., or any surviving or related corporate entity. All trademarks remain the property of their respective owners. All information presented herein should be considered the result of an un-moderated public forum with no responsibility for its accuracy or usability assumed by the users and sponsors of this site or any corporate entity. | |||||
The Forum | Parts and Services | Unofficial Allis Store | Tractor Shows | Serial Numbers | History |
Rebuilding a 301 diesel ; how many hours ?? |
Post Reply ![]() |
Author | |
DougG ![]() Orange Level ![]() Joined: 20 Sep 2009 Location: Mo Points: 8200 |
![]() ![]() ![]() ![]() ![]() Posted: 10 Feb 2011 at 6:48pm |
Wondering how many hours are involved in rebuilding an AC 301 diesel engine oil pan to valve cover , new sleeves , valves etc ; owner of a tractor wants to rebuild , I,ve never done one but can pull the engine or get it ready for an in frame job ; need a figure ; Thanks
|
|
![]() |
|
Sponsored Links | |
![]() |
|
Orange Blood ![]() Orange Level ![]() ![]() Joined: 29 Nov 2010 Location: ColoradoSprings Points: 4053 |
![]() ![]() ![]() ![]() ![]() |
That is going to depend on how much machining of head , crank, or block is required, what parts you will have to wait on. We (2 grown men, both mechanics) tore down and rebuilt a 190XT in a weekend, just two of us, but we had all of the parts in hand ahead of time, no grinding of the crank or head, just had lots of blow bye from a bad air filter. If memory serves we had the engine out of the tractor in 4 hours, engine tore down and stripped in another couple of hours. Started washing parts that night, had everything but the head clean by 10 o'clockish. Next morning started early, ground the valves, cleaned the head, had the engine back to gether by around 1-2ish. Tractor running by suppertime, and out of the shed with all tin back on by midnight. Long couple of days, but we had to keep the tractor in service, it was hay season.
|
|
Still in use:
HD7 WC C CA WD 2-WD45 WD45LP WD45D D14 3-D17 D17LP 2-D19D D19LP 190XTD 190XTLP 720 D21 220 7020 7030 7040 7045 3-7060 Projects: 3-U UC 2-G 2-B 2-C CA 7-WC RC WDLP WF D14 D21 210 7045 N7 |
|
![]() |
|
DrAllis ![]() Orange Level Access ![]() Joined: 12 Sep 2009 Points: 21049 |
![]() ![]() ![]() ![]() ![]() |
I used to bid in-frames at 24 to 32 hrs depending on things. New pistons, sleeves, rings, roll in mains and rods (always new rod bolts!!), front and maybe rear seal (depends if it might have had a semi-recent clutch which would have got a rear seal and clutch shaft seal at that time) new injector tips and maybe rebuild the water pump. All cylinder head work done by local machine shop so none of my labor on that. Conn rod pin bushings seldom need replacement on non-turbo engine. If you get into cam brg replacement, then you're talking about a lot more time involved.
|
|
![]() |
|
DougG ![]() Orange Level ![]() Joined: 20 Sep 2009 Location: Mo Points: 8200 |
![]() ![]() ![]() ![]() ![]() |
I,m not real sure what exactly is going on inside it yet , rattles , but when it heats up she has a knock down low , could get expensive .! ???
|
|
![]() |
|
Orange Blood ![]() Orange Level ![]() ![]() Joined: 29 Nov 2010 Location: ColoradoSprings Points: 4053 |
![]() ![]() ![]() ![]() ![]() |
Better plan on some extra hard parts, and machining work!!! Could be a wrist pin, but those tend to stay up high, and tend to go away when warm, guess the crank and a rod are suspect huh?
|
|
Still in use:
HD7 WC C CA WD 2-WD45 WD45LP WD45D D14 3-D17 D17LP 2-D19D D19LP 190XTD 190XTLP 720 D21 220 7020 7030 7040 7045 3-7060 Projects: 3-U UC 2-G 2-B 2-C CA 7-WC RC WDLP WF D14 D21 210 7045 N7 |
|
![]() |
|
sandylakeimplement ![]() Orange Level ![]() ![]() Joined: 18 Sep 2009 Location: Sandy Lake, PA Points: 399 |
![]() ![]() ![]() ![]() ![]() |
We figure 50 hours for in frame but we do it all in-house including head and injector reconditioning and con rod bushing replacement/honing. Also includes a couple hours for resurfacing the o ring bore in each cylinder bore of the block. I estimate an additional 11 hours for out of frame which covers time for cam bushings,front & rear seals, injection pump idler bearings, hyd drive bearings, clutch, torque tube seal replacement and other sundries. With luck it could come in several hours less but I try to prepare the owner for something other than a best case scenario. Nobody has ever objected to the invoice being less! Bill
|
|
Sandy Lake Implement
Sandy Lake, PA 724-376-2489 www.sandylakeimp.com FIND US ON FACEBOOK |
|
![]() |
|
skipwelte ![]() Orange Level ![]() Joined: 29 Oct 2009 Location: Anthon, Iowa Points: 723 |
![]() ![]() ![]() ![]() ![]() |
Somewhere aroung 40 - 50 hrs on a rebuild. A lot and I mean a lot depends on how much you do, like valves and seats, cam bushings, wrist pin bushings. If your just gonna slide in sleeves and pistons then yer around 25 hrs, but thats not an overhaul except to a salesman!!! There is always something that you dont plan on that will bite in the butt. HTH |
|
![]() |